Net Billing Explained — Pakistan's February 2026 Solar Rules

Net metering is over for new connections. Here is what replaced it, in plain words.

On 9 February 2026, NEPRA's Prosumer Regulations (S.R.O. 251(I)/2026) replaced net metering with net billing for all new rooftop solar connections. The change is one number that matters: what the grid pays you for the electricity you send back.

Not a government website. This page explains the rules as notified; your DISCO's net-billing agreement is the authority for your connection.

Old net metering (pre-Feb 2026 agreements)Exported units credited at about Rs 25.32/unit — well below the top retail slabs
Net billing (new connections)Exported units bought at Rs 8.13/unit (rate for Apr–Jun 2026, NEPRA S.R.O. 1501(I)/2026); you still pay the full retail tariff on every unit you import
Agreement length5 years (was 7 under net metering), renewable by mutual consent; NEPRA can revise the export rate during the term
Size limitUp to your sanctioned load, maximum 1 MW; no new connection if the local transformer is already 80% loaded
SourceNEPRA (Prosumer) Regulations 2026, S.R.O. 251(I)/2026 — checked 27 November 2026

What this means for a home buying solar today

Checker: am I protected on the old net metering?

Answer both questions to see your position.

How to apply for a net billing connection

  1. Check your sanctioned load and phase. Your system cannot exceed your sanctioned load; most DISCOs require a three-phase connection for larger systems.
  2. Install with an AEDB-certified installer using approved inverter and protection equipment — uncertified installs are the commonest reason applications stall.
  3. Apply through your DISCO (for PITC companies, the application starts on the DISCO's net-metering portal; K-Electric has its own process). Documents usually asked: CNIC, latest paid bill, system documents and inverter certificates.
  4. Inspection and agreement. The DISCO inspects, a bi-directional meter is installed, and you sign the 5-year net billing agreement.
  5. Read your first bill carefully. Imported and exported units are shown separately; exports are credited at the notified rate (Rs 8.13/unit for Apr–Jun 2026).

Timelines vary widely by DISCO — the full process commonly takes 30–90 days. Homes up to 25 kW were reported exempt from the NEPRA concurrence fee from April 2026; confirm the current fee position with your DISCO when you apply, as this detail has changed more than once.

Net billing vs the old net metering

Under the old net metering, agreements signed before 9 February 2026 credited exported units at about Rs 25.32 per unit — the national average power purchase price. Under net billing (NEPRA S.R.O. 251(I)/2026, 9 February 2026), exports are credited at Rs 8.13 per unit — the national average energy purchase price. That one change is why a system sized to your daytime use matters so much more now.

The two schemes are also netted differently. Old net metering netted units against units. Net billing nets rupees against rupees in each 30-day billing cycle: imports are billed at your retail tariff, exports are credited at Rs 8.13, and you pay the difference. If your exports are worth more than your imports in a cycle, the surplus is credited to the next cycle or paid quarterly.

The full step-by-step application guide: see the net metering guide.