How to Get a New Electricity or Gas Connection
Documents, fees and timelines — and the one warning to read before you pay anything.
A new domestic electricity connection is applied for online through the ENC portal or on a free paper form at the sub-division office, and ends with a demand notice and a meter installation. A new gas connection is a different story: it is only given on imported RLNG tariff now, and whether applications are even open is disputed. Both are explained below.
Not a government website. The binding figure for any connection is always the demand notice your company issues after inspection — never a figure from a website.
New electricity connection
Who needs it: the owner or tenant of a premises with no existing connection, or anyone needing a second meter or a load extension.
Documents needed
- Ownership proof (registry or allotment letter).
- Affidavit on Rs 50 stamp paper — that there is no earlier connection, that you will pay any old dues found later, and that you are not a defaulter elsewhere.
- Attested CNIC copies of the applicant and one witness (plus the owner's, if you are renting); owner's NOC if you are a tenant.
- A neighbour's bill or 14-digit reference number (the ENC online form requires it).
- Wiring contractor's test report.
- For the ENC online form: five scanned files, JPG or PDF, up to 300 KB each.
Source: NEPRA Consumer Service Manual (revised 26 Nov 2025), clause 2.3, as read in dated secondary sources.
Steps
- Apply at enc.com.pk (it serves LESCO, GEPCO, PESCO, HESCO, SEPCO, QESCO, TESCO and HAZECO; IESCO, FESCO and MEPCO have their own ENC portals or apps) or on the free form at the sub-division office. Keep the tracking ID or acknowledgement receipt.
- Site inspection and load sanction. A demand notice (DN) is issued — pay only the DN amount, at the designated bank or through ENC "Pay DN", within 30 days (a further 30 days' grace may be allowed).
- Sign the power supply contract in triplicate after payment. The DISCO then installs and seals the meter and energises the connection.
- Timeline (NEPRA manual, Annexure III): 30 days from registration to meter for loads up to 15 kW; 44 days for 15–70 kW.
Fees — electricity
| Security deposit (residential, urban) | Rs 1,220/kW — for example, a 5 kW urban home pays Rs 6,100 |
| Security deposit (residential, rural) | Rs 610/kW |
| Connection charges | Actual material cost at store issue rate + 12% store handling + 8% installation on that subtotal — site-specific, no fixed total exists |
The deposit rates are from the NEPRA manual (Annexure IV), notified by S.R.O. 04(I)/2011 and still charged. The deposit is refundable when the connection is permanently removed with no dues outstanding, within 30 days of the request. Note that in February 2025 NEPRA heard DISCO petitions to raise deposits many times over (LESCO asked for Rs 19,272/kW urban) and withheld its decision pending audit — so deposit rates could change; re-check before applying. Total meter cost: no verified total exists. One blog quotes around Rs 21,300 for a standard single-phase connection, but that figure is not from LESCO or NEPRA and is not corroborated, so we do not publish it — the demand notice after inspection is the only binding figure. K-Electric has its own schedule of charges (not ENC); new KE connections go through ke.com.pk or the KE Live app.
New gas connection (SNGPL / SSGC)
Who needs it: households in Punjab, Khyber Pakhtunkhwa, Islamabad and Azad Kashmir (SNGPL) or Sindh and Balochistan (SSGC), where a gas main already runs in front of the house.
Documents needed
- Valid CNIC copy.
- Property title document (registry, transfer certificate or fard).
- Owner's NOC if the property is not in your name.
- Nearest neighbour's gas bill or consumer number (mandatory for the online application).
- Electricity bill for the address (helpful); signed RLNG supply contract; house-line plan.
Steps
- Confirm a gas main runs in your street. If not, a separate network-extension form is needed.
- Apply online at sngpl.com.pk ("Apply for New Connection" under Online Services) or through the ConnectOn app, or in person at a regional office. Choose Normal Merit or Fast Track.
- Keep the acknowledgement receipt.
- Site survey, then a demand notice or proposal letter, a house-line plan and a list of registered contractors.
- Pay at the named bank; the service line is laid and the meter installed.
Fees — gas (SNGPL, from SNGPL's own site as read 14 Nov 2026)
| Applying | No fee |
| Up to 10 marla | Service line Rs 1,500 + refundable security Rs 20,000 = Rs 21,500 |
| Above 10 marla | Service line Rs 3,000 + security Rs 20,000 = Rs 23,000 |
| Fast Track (optional, on top) | Rs 25,000. Same form for Normal Merit and Fast Track. |
SNGPL notes OGRA may change these charges — check the challan before paying. For SSGC (Sindh and Balochistan), secondary readings of SSGC's online page (8 Nov 2026) quote: up to 10 marla or 300 sq yd — Sindh Rs 22,725, Balochistan Rs 21,725; over 10 marla — Sindh Rs 24,450, Balochistan Rs 23,450 (the Sindh total includes Rs 1,000 stamp duty). These SSGC figures were not opened directly from ssgc.com.pk, so treat them as secondary. Important: a new connection gets RLNG at a flat rate, not the slab-wise system-gas rates — it is usually costlier. Old applicants who paid under system gas pay a differential (Rs 15,500 where Rs 4,500 was already deposited, to reach the Rs 20,000 security). The reported backlog is 700,000+ applications; normal processing is reported at 2–3 years and fast track at 6–12 months — neither is a guaranteed date.
Common mistakes
- Paying any amount to a middleman or agent outside the sealed demand notice.
- Applying without the neighbour's bill reference or the wiring test report — the two most-forgotten documents for electricity.
- Declaring too little load — the meter and connection must match your actual appliances; extending the load later means a fresh deposit on the additional kW (Rs 1,220/kW urban).
- Paying a fast-track fee before confirming applications are open (gas).
- Assuming a new gas connection gets cheap system-gas slabs — it gets the RLNG flat rate.
- Applying where no gas main exists in the street, or expecting a quick connection after years of queue.
Frequently asked questions
How long does a new electricity connection take?
Under the NEPRA manual, 30 days from registration to meter for loads up to 15 kW, and 44 days for 15–70 kW. The demand notice must be paid within 30 days, with a further 30 days' grace sometimes allowed.
Is the security deposit refundable?
Yes — when the connection is permanently removed and no dues are outstanding, the deposit is refunded within 30 days of the request.
Can I get a new gas connection on cheap system gas?
No. New domestic connections are only on imported RLNG tariff, charged at a flat rate rather than slab-wise. System-gas connections remain banned for new applicants.
What if there is no gas main in my street?
You need a separate network-extension form first. Applying for a connection alone will not bring the main to your street.